| | | | | | | |  | City Council
Staff Report
|
|
| | | | | | | |
Subject: | Amendment No. 1 to the Contract Services Agreement with Q-Free America, Inc. for the Advance Management System, Services & Support |
|
| Date: | July 27, 2021 |
|
| Submitted By: | Justin Nartker, Director of Public Services
Matt McClure, Public Services Manager |
|
| Department: | Public Services |
|
| | | | | | | | Staff Recommendation: | Adopt a Resolution of the City Council of the City of Rocklin Approving Amendment No. 1 to the Contract Services Agreement with Q-Free America Inc. for Advanced Traffic Management System, Services & Support, and Authorizing the City Manager to Execute the Amendment.
|
|
| | | | | | | | BACKGROUND: | On October 13, 2020, the City Council adopted Resolution 2020-191, authorizing a Contract for Services with Q-Free America, Inc. for the Advanced Traffic Management System (ATMS). This management system will interconnect and synchronize the traffic signals within the City. The total contract amount was $151,833.66, with City Manager change order authority of five percent of the contract $7,592 (rounded), for a total not to exceed amount of $159,426 (rounded). A total of $149,492 (rounded) was paid in Fiscal Year (FY) 2020/21, leaving approximately $10,000 remaining that will be spent on contract specified tasks.
During the and contract negotiation and execution processes, it was not anticipated that sales tax would be charged; however, the contractor has incurred $7,251 (rounded) in additional charges on taxable items. Staff recommends the total authorized contract amount be increased to $166,677.
Sales Tax (SB325) and Landscaping and Lighting Maintenance 2 (L&L2) funding are available to cover the additional cost and no budget appropriation is necessary at this time. This project is included in the FY 2021/22 Budget that was adopted by the City Council on June 22, 2021.
|
|
| | | | | | | | Fiscal Impact: | No additional fiscal impact has been identified as the amounts noted in this request are available in the FY 2021/22 Budget adopted by the City Council. The accounts are noted in the table below to demonstrate available funding.
Account
|
Current Budget
|
Expended to Date
|
Available Budget
|
21082477070
|
$81,600
|
0
|
$81,600
|
23582477070
|
$77,400
|
0
|
$77,400
|
|
|
| | | | | | | | This Staff Report has been reviewed by the City Attorney for legal sufficiency and by the City Manager for content. |
| | | | | | | | The Finance Department has reviewed this staff report and certifies that budgeted funds are available, unless a budget amendment is being requested as part of this action item. |
|