Item Coversheet

Item Number 14.

  

City Council 
Staff Report


Subject:Bid for the Winding Lane Curve & Lost Avenue Intersection Improvement Project


Date:August 10, 2021


Submitted By:

Justin Nartker, Director of Public Services

Matt McClure, Public Services Manager



Department:Public Services

Staff Recommendation:

Adopt a Resolution of the City Council of the City of Rocklin Awarding the Contract for the Winding Lane Curve & Lost Avenue Intersection Improvement Project to Central Valley Engineering and Asphalt, Inc. and Authorizing the City Manager to Execute the Agreement.
BACKGROUND:

The Winding Lane Curve & Lost Avenue Intersection Improvement Project (Exhibit A) was included in the 2022-2026 Capital Improvement Plan and the Fiscal Year (FY) 2021/22 budget adopted by the City Council on June 22, 2021.  This project consists of widening the roadway along the curve  at Winding Lane to expand the roadway to meet current City standards; and install curb, sidewalk, and gutter at the intersection  Lost Avenue and Winding Lane.

 

The Winding Lane Curve & Lost Avenue Intersection Improvement Project invitation for bids was advertised on June 11, 2021, and June 18, 2021, with the bid opening on June 22, 2021.  Five (5) bids were received, as listed below, with Central Valley Engineering and Asphalt, Inc. submitting the lowest bid in the Amount of $312,775.

 

 

Bidder’s Name                                                                                    Bid Amount                                    

Central Valley Engineering and Asphalt, Inc. (Roseville)                  $ 312.775.00

Gabe Mendez, Inc. (Newcastle)                                                            $ 367,984.00

Martin General Engineering, Inc. (Rancho Cordova)                        $ 369,469.50

Western Engineering, Inc. (Loomis)                                                    $ 381,190.00

J.D. Pasquetti Engineering LLC (Lincoln)                                             $ 386,446.90

 

Staff has reviewed the bids for sufficiency and recommends the City Council award the contract to Central Valley Engineering and Asphalt, Inc., with the lowest bid in the amount of $312,775.  The Rocklin Municipal Code section 3.04.050 authorizes a contingency amount of fifteen percent of the contract ($46,917 (rounded)) for a total authorized Project amount of $359,692 (rounded).

 

As part of this project, staff met with South Placer Municipal Utility District (SPMUD) who requested that the City perform the necessary work on the sewer infrastructure e.g. raising/installing manholes.  The cost for this work is estimated at $13,940. The City and SPMUD are entering into a reimbursement agreement for the work. Pursuant to the agreement, SPMUD will reimburse City for the cost associated with the utility work in  an amount not to exceed $22,500, to account for any additional costs identified during construction. 

 

This project is funded through the SB325 Gas Tax Fund (210). The original budget for this project is $292,100, which is below the lowest bid amount of $312,775.  This is due to the recent pricing increases that are being experienced nationwide.  As a result, once the change order authority of $46,917 (rounded) and the estimated SPMUD reimbursement of $13,940 are factored in, a budget appropriation in the amount of $53,652 is necessary and may necessitate a budget amendment.

 


Environmental Analysis:

The City of Rocklin’s Environmental Coordinator has reviewed the Winding Lane Curve & Lost Avenue Intersection Improvement Project and determined that it falls under the previously approved Notice of Exemption for the City’s road resurfacing projects, Resolution of the City Council of the City of Rocklin 2019-236, and is exempt from review under the California Environmental Quality Act (CEQA) pursuant to California Code of Regulations Section 15301 & 15302.


Fiscal Impact:

This project is included in the FY 2021/22 Budget and is funded using SB325 Gas Tax Funds (210).  This project came in over budget and an appropriation of $53,652 will be necessary and may necessitate a budget amendment.   

 

 

Account

Current Budget

Expended to Date

Available Budget

Requested Appropriations Inc/(Dec)

21082677070

$774,600

$0

$774,600

$53,652


ATTACHMENTS:
Description
Resolution A
Resolution A - Exhibit A
This Staff Report has been reviewed by the City Attorney for legal sufficiency and by the City Manager for content.
The Finance Department has reviewed this staff report and certifies that budgeted funds are available, unless a budget amendment is being requested as part of this action item.