Item Coversheet

Item Number 14.

  

City Council 
Staff Report


Subject:Award Contract for the Sceptre, Camelot, and Midas Repair Project


Date:August 24, 2021


Submitted By:

Justin Nartker, Director of Public Services          

Matt McClure, Public Services Manager



Department:Public Services

Staff Recommendation:

Adopt a Resolution of the City Council of the City of Rocklin Awarding the Contract for the Sceptre, Camelot, and Midas Repair Project to PBM Construction, Inc. and Authorizing the City Manager to Execute the Agreement.
BACKGROUND:

The Sceptre Drive and Camelot Drive Repair Project and the Midas Avenue Drainage Repair Project were included in the 2022-2026 Capital Improvement Plan (CIP) and the Fiscal Year (FY) 2021/22 budget adopted by the City Council on June 22, 2021.  The Sceptre Drive and Camelot Drive Repair consists of repairing the roadway  along the creek crossing at Sceptre Drive and Camelot Drive.  The budget amount identified for this project was $480,000 with $130,000 budgeted in FY 2021/22 and $350,000 projected in FY 2022/23. The Midas Repair Project consists of replacing failed drainage infrastructure, with a FY 2021/22 budget of $165,000. The total combined budget amount for these projects are $295,000 in FY 2021/22 and $350,000 identified in FY 2022/23, for a total project amount of $645,000.

 

Staff reviewed the projects and determined that completing the Sceptre Drive and Camelot Drive Repair project at the same time as the Midas Avenue Repair project would be more cost effective (e.g. mobilization, better pricing, expand competitive interest in jobs of similar scope, streamline environmental permits). 

 

The Sceptre, Camelot, and Midas Repair Project invitation for bids was advertised on July 9, 2021, and July 16, 2021, with the bid opening on July 29, 2021.  Four (4) bids were received, as listed below, with PBM Construction, Inc. submitting the lowest bid in the Amount of $475,154.

 

Bidder's Name (Location)                                        Bid Amount

PBM Construction, Inc. (Rocklin)                                  $475,154

Western Engineering, Inc. (Loomis)                             $532,010

Martin General Engineering, Inc. (Ranch Cordova)   $606,400

Gabe Mendez, Inc. (Newcastle)                                    $608,886

 

Staff has reviewed the bids for sufficiency and recommends the City Council award a contract to PBM Construction, Inc., in the amount of $475,154.  The Rocklin Municipal Code section 3.04.050 authorizes a contingency amount of fifteen percent of the contract ($71,273 (rounded)) for a total authorized Project amount of $546,427(rounded).

 

Both CIP projects are funded through the SB325 Gas Tax Fund (210).  By combining both projects in FY 2021/22, the overall cost will be reduced by approximately $99,000.  Although the total cost of the project will be less, the amount budgeted for FY 2021/22 does not include the FY 2022/23 amount and a budget appropriation in the amount of $251,427 is necessary and may necessitate a budget amendment.


Environmental Analysis:
The City of Rocklin’s Environmental Coordinator has reviewed the Sceptre, Camelot, and Midas Repair Project and determined that it falls under the previously approved Mitigated Negative Declaration of Impact that was prepared and adopted by the City Council on August, 11, 2020 (Resolution 2020-152).
Fiscal Impact:

This project is included in the FY 2021/22 Budget and is funded using SB325 Gas Tax Funds (210).  The project came in over budget and an appropriation of $251,427 will be necessary and may necessitate a budget amendment.  

 

 

Account

Current Budget

Expended to Date

Available Budget

Requested Appropriations Inc/(Dec)

21082677070

$774,600

$0

$774,600

$251,427


ATTACHMENTS:
Description
SR Exhibit A
Resolution A
Resolution A - Exhibit A
This Staff Report has been reviewed by the City Attorney for legal sufficiency and by the City Manager for content.
The Finance Department has reviewed this staff report and certifies that budgeted funds are available, unless a budget amendment is being requested as part of this action item.