Item Coversheet

Item Number 13.

  

City Council 
Staff Report


Subject:

Amending the Consultant Services Agreement for the Preparation of an Environmental Impact Report for the College Park Project and the Agreement with Evergreen Sierra East LLC for Payment of the Cost of Preparation of the Environmental Impact Report, and Approving Additional Budget Appropriations.



Date:February 8, 2022


Submitted By:David Mohlenbrok, Director of Community Development    


Department:Community Development

Staff Recommendation:

Adopt a Resolution of the City Council of the City of Rocklin Authorizing the City Manager to Execute Amendment No. 2 to the Consultant Services Agreement with De Novo Planning Group for the Preparation of an Environmental Impact Report for the College Park Project, and Amendment No. 2 to the Agreement with Evergreen Sierra East, LLC for Payment of Cost of Preparation of the Environmental Impact Report, and Approving Additional Budget Appropriations.

BACKGROUND:

College Park (formerly Sierra Villages) is a 108.4-acre project comprised of two sites, the North Village (72.6 acres) on the northeast corner of Rocklin Road and Sierra College Boulevard, and the South Village (35.8 acres) on the southeast corner of Rocklin Road and El Don Drive. The project is proposed to be developed into a Planned Development (PD) featuring parks, open space and trails surrounded by residential and mixed uses (retail, office, medical, and institutional uses). It was determined that an Environmental Impact Report was needed to process the project for purposes of complying with the California Environmental Quality Act (CEQA). De Novo Planning Group was selected to perform that work, as overseen by the City. Through a three-party arrangement, the City oversees and manages the effort and the project, and the project applicant funds the cost of the EIR.

 

On April 25, 2017 the City Council approved an Agreement for Payment of Cost of Preparation of an Environmental Impact Report (EIR) and a Consultant Services Agreement for an Environmental Impact Report (EIR) for the College Park project.

 

On August 24, 2021 the City Council approved and authorized the City Manager to execute Amendment No. 1 to the Consultant Services Agreement with De Novo Planning Group for the preparation of an Environmental Impact Report for the College Park project and Amendment No. 1 to the Agreement with Evergreen Sierra East LLC for payment of cost of preparation of the Environmental Impact Report, and approving additional budget appropriations in the amount of $14,390; this amendment increased the $146,695 contract amount and reimbursement amount to $161,085.

 

Based on the volume of public comment letters on the Draft EIR requiring written responses in excess of what was included in De Novo Planning Group’s original scope of work, it has been determined that a second amendment to the Agreement for Payment of Cost of Preparation of an Environmental Impact Report and to the Consultant Services Agreement for the Preparation of an Environmental Impact Report on the College Park project is necessary. Amendment No. 2 is for $19,140 and will be fully funded by the project applicant.

Fiscal Impact:

Amendment No. 2 to the Consultant Services Agreement with De Novo Planning Group for the College Park EIR is for $19,140, for a new Contract total not-to-exceed amount of $180,225. The applicant will fully reimburse the City for the EIR cost.

 

In addition, Amendment No. 2 will necessitate increases to the revenue and expenditure budgets in the Community Development Department budget in the amount of $19,140 in the General Fund (100) to account for the EIR expenses and reimbursements from the applicant.

ATTACHMENTS:
Description
Resolution
This Staff Report has been reviewed by the City Attorney for legal sufficiency and by the City Manager for content.
The Finance Department has reviewed this staff report and certifies that budgeted funds are available, unless a budget amendment is being requested as part of this action item.