Item Coversheet

Item Number 13.

  

City Council 
Staff Report


Subject:Contract for Finnish Temperance Hall & Rocklin Event Center Out-Building Roof Replacements


Date:April 12, 2022


Submitted By:

Justin Nartker, Director of Public Services

Matt McClure, Public Services Manager



Department:Public Services

Staff Recommendation:

Adopt a Resolution of the City Council of the City of Rocklin Awarding the Contract for Finnish Temperance Hall & Rocklin Event Center Out-Building Roof Replacements to MCM Roofing Company, Inc. and Authorizing the City Manager to Execute an Agreement with MCM Roofing Company, Inc.

BACKGROUND:

The Finnish Temperance Hall & Rocklin Event Center Out-Building Roof Replacements project was included in the Fiscal Year (FY) 2021/22 Capital Projects budget approved by the City Council on June 22, 2021. This project consists of removing and replacing the roofs located at the Finnish Temperance Hall and the Rocklin Event Center Out-Building. Project locations maps are included as Exhibits 1 and 2.

 

The invitation for bids for the Finnish Temperance Hall & Rocklin Event Center Out-Building Roof Replacements project was advertised on February 4, 2022, and February 11, 2022, with the bid opening Wednesday, March 2, 2022. One (1) Bid was received from MCM Roofing Company, Inc. in the amount of One Hundred and Twenty-Two Thousand, Nine Hundred Dollars ($122,900). See Exhibit 3 for the Bid Summary Sheet.

 

Staff has reviewed the bid for sufficiency and determined it was responsive. Staff recommends that the City Council award the contract to MCM Roofing Company, Inc. and establish the City Manager’s change order authority at Fifteen (15) percent of the contract ($18,435).

 

The Event Center Out-Building is funded out of the General Fund (100) and no budget appropriation is necessary. The Finnish Temperance Hall is funded out of the Public Facilities Impact Fees (308), and a budget appropriation in the amount of $51,320 will be necessary and may necessitate a budget amendment. The  amount for this project including Fifteen (15) percent change order authority brings the total cost to $141,335.

Fiscal Impact:

This project is included in the FY 2021/22 Capital Budget and is funded using General Funds (100) for the Event Center Out-Building and Public Facilities Impact Fees (308) for the Finnish Temperance Hall. A  budget appropriation for funding from the Public Facilities Impact Fees (308) in the amount of $51,320 will be necessary and may necessitate a budget amendment.

ATTACHMENTS:
Description
Resolution
Resolution Exhibit A - Agreement with MCM Roofing Company, Inc.
Exhibit 1 - Project Location Map (Finnish Temperance Hall)
Exhibit 2 - Project Location Map (Rocklin Event Center)
Exhibit 3 - Bid Summary Sheet
This Staff Report has been reviewed by the City Attorney for legal sufficiency and by the City Manager for content.
The Finance Department has reviewed this staff report and certifies that budgeted funds are available, unless a budget amendment is being requested as part of this action item.